Future
Development (
Estimated cost of all the development projects Rs. 3360 crores.)
The anticipated traffic by
2012-13 is 80 MT necessitating augmentation of port capacity by 45
MT.
Accordingly the following
projects have been formulated for augmentation of capacity.
|
DEEPENING OF CHANNELS |
-
Phase-I
deepening of the entrance channel and turning circle of Inner
harbour to facilitate navigation of Panamax vessels with 11
mtrs. draft vessels is under progress. (Expected date of
completion: October, 2006)
-
Phase-II
deepening of inner harbour to handle Panamax vessels upto 14
meters draft will be taken up in 2007-08 (Expected date
of completion: December, 2007)
-
Deepening of
Outer Harbour Approach Channel, Turning circle to handle
vessels upto 200,000 DWT will be taken up during 2007-08.
-
Deepening and
strengthening of Ore berth to cater to 200,000 DWT vessels
will be taken up in 2008-09
|
|
STRENGTHENING OF EXISTING BERTHS |
-
4 berths viz.,
EQ-7, WQ-1 to WQ-3 are proposed to be strengthened and
deepened to facilitate Panamax vessels upto 12.5 meters draft.
in 2007-08.
-
2 berths WQ1,
and WQ2 are being strengthen to cater 11 meters draft vessels.
-
2 berths WQ4 and
WQ5 will be strengthened and deepened to cater 12.5 meters
draft2008-09.
-
4 berths viz.,
EQ-1 to EQ-4 which were built during 1930s are proposed to be
upgraded to 14 meters draft in 2008-09.
-
Proposal to
construct WQ-8 berth and install mechanized ship shore loading
facilities for export of alumina is planned in 2008-09
-
Installation of
mechanized facilities at WQ-7 berth for exports of alumina is
planned in 2007-09.
-
Installation of
integrated mechanized handling facility for ship shore
discharge and loading into wagons at general cargo berth is
planned during 2008-09.
-
Up gradation of
iron ore handling facility at Outer harbour during 2009-10 at
a cost of 190 corers is under consideration.
|
|
CONSTRUCTION OF NEW BERTHS UNDER PPP |
|
|
|
LOGISTICS IMPROVEMENTS |
-
Additional Link
Road connecting to National Highway with the operational area
is under construction as a joint venture with National
Highways Authority of India and is expected to be commissioned
by September 2006.
-
Improvement to
internal road net work in the operational area by constructing
road fly avers, 4 lane road, strengthening of existing roads,
provision of additional access to NH-5 etc., at an estimated
cost of Rs. 240 crores in 2 phases in planned.
-
2 Transit sheds
of 4350 sq meters is under construction ( Anticipated date of
completion: September, 2006)
-
4 Nos. open
storage sheds of 20730 sq meters will be provided by June,
2008
-
Development of
stacking area at east yard dumps close to the outer harbour
area has been taken up.
-
Procurement of
additional tugs and replacement of cranes.
-
Replacement of
tugs / floating crafts / Locos.
-
Revamping and
strengthening of rail connectivity.
-
The most
prestigious project coming up at VPT is development of LPG
cavern facility - First of its kind in South Asia-. This is
being developed by South Asia LPG Co. Ltd., a JV between HPCL
and TOTAL and envisages mined rock cavern at a depth of 162
meters below sea level with acapacity to store 60,000 tonnes
of LPG. The Project is expected to be completed by September,
2007
|
|